Industrial plants, shutdown and maintenance work

Turnaround of Burghausen refinery

OMV Deutschland GmbH commissioned Kraftanlagen München with the execution of all pipeline-related tasks in the Burghausen refinery during the 2014 general shutdown. The scope of the order included providing materials, disassembly and reassembly of pipelines and brackets, execution of integration tasks, coordination of painting, insulation, NDT and scaffolding. KAM was able to achieve the superordinate project objective of zero accidents.

Fact sheet

Customer:
OMV Deutschland GmbH, Burghausen


Period of execution:
October 2014


Plant parameters:

  • Materials: Carbon steel, 1.4462, 1.4541, 1.4571, 10CrMo9-10, 12CrMo19-5, 13CrMo4-5, 16Mo3
  • Construction period core shutdown: 26 days
  • Peak personnel: 571 employees
  • Hours worked: approx. 180,000
  • Number of weld seams: approx. 1,000
  • Number of blanking discs: approx. 1,000
  • Number of welded integration points: approx. 900