Industrial plants, shutdown and maintenance work

Turnaround of Burghausen refinery

OMV Deutschland GmbH commissioned Kraftanlagen München with the execution of all pipeline-related tasks in the Burghausen refinery during the 2014 general shutdown. The scope of the order included providing materials, disassembly and reassembly of pipelines and brackets, execution of integration tasks, coordination of painting, insulation, NDT and scaffolding. KAM was able to achieve the superordinate project objective of zero accidents.

Fact sheet

Customer:
OMV Deutschland GmbH, Burghausen

Period of execution:
October 2014

Plant parameters:

  • Materials: Carbon steel, 1.4462, 1.4541, 1.4571, 10CrMo9-10, 12CrMo19-5, 13CrMo4-5, 16Mo3
  • Construction period core shutdown: 26 days
  • Peak personnel: 571 employees
  • Hours worked: approx. 180,000
  • Number of weld seams: approx. 1,000
  • Number of blanking discs: approx. 1,000
  • Number of welded integration points: approx. 900


Additional projects

ImprintData ProtectionGeneral Terms and ConditionsDownloads for Business Partners
In order to optimally design and permanently update this website, we are using cookies (amongst others for: Google Analytics). By continuous usage of this website, you'll agree to their usage. More information about this, the usage of your personal data and your disagreement options can be found in the data privacy statement.