Industrial plants, shutdown and maintenance work

MiRO turnaround

MiRO commissioned Kraftanlagen München GmbH with pipeline-related work during the general shutdown of 3 parts of the plant. The scope of the order included the disassembly and reassembly of pipelines including the non-destructive examinations and heat treatment, blanking discs and valve programs (partially while needing heavy duty respiratory protection), the coordination of scaffolding, insulation and cranes. The work was completed with no accidents.

Fact sheet

Customer:
MiRO Gmbh & Co. KG

Period of execution:
2014 - 2015, core standstill March 2015 (32 days)

Technical data:

  • Peak personnel: 288 employees
  • Hours worked: approx. 120,000
  • Weld seams: 4,334
  • Valves:  384
  • Blanking discs: 182


 

Additional projects

ImprintData ProtectionGeneral Terms and ConditionsDownloads for Business Partners
In order to optimally design and permanently update this website, we are using cookies (amongst others for: Google Analytics). By continuous usage of this website, you'll agree to their usage. More information about this, the usage of your personal data and your disagreement options can be found in the data privacy statement.