Fabrication, industrial and plant construction

Prefabrication of the vinyl acetate-monomer plant

Our scope of delivery included the new construction and/or the conversion of the CO2 scrubber as well as the prefabrication of pipelines.

Fact sheet

Customer:
Wacker Chemie AG, Burghausen

Period of execution:
02/2012 – 04/2012

Technical data:

  • Processed pipe in metres: 1,145
  • Material: 1.4571
  • Resources: 20
  • Hours worked: approx. 6,500