How to get in touch with us:

Any questions? Get in touch!

You can reach us at: +49 89 6237-0

Fabrication, power plant technology

Moorburg power plant, Block A, B and Y

As part of the new construction of a hard coal-fired power plant in Hamburg-Moorburg, Kraftanlagen München was commissioned with erecting the medium pressure/low pressure piping systems in January 2008. FINOW in Eberswalde was responsible for fabrication.

Fact sheet

Customer:
Vattenfall Europe Generation AG

Period of execution:
January 2008 - November 2012

Scope of service:

  • Feed water, auxiliary steam system, extraction steam for main condensate pre-heating, main condensate,
    hot water supply and return, hot water storage
  • Process steam system including condensate recirculation
  • Total weight: approx. 2,600 t
  • Total length: approx. 34,800 m
  • Number of weld seams: approx. 19,500
  • Materials: 16Mo3, 10CrMo9-10, X6CrNiTi8-10


 

 

 