Beznau nuclear power plant - replacement of a live steam pipe bend DN 600

Kraftanlagen Heidelberg was tasked with supplying and installing a pipe bend DN600 in the live steam pipe. The replacement took place during a revision in Block 1 of the Swiss Beznau nuclear power plant (NOK).

The contract included the following services:

  • Engineering
  • Inventory for disassembly and installation
  • VPU creation for fabrication and installation
  • Supply of a new, inductive bend and subsequent straight pipeline components DN600 in accordance with requirement specifications. Material 13CrMo44, 90° R=2,400 mm
  • Installation
  • Heat treatment
  • Execution and organisation of non-destructive material tests and approvals
  • Documentation

Fact sheet

Customer: 
Nordostschweizerische Kraftwerke AG


Technical data:

  • Procurement of a new, inductive bend and subsequent straight pipeline components DN600 in accordance with requirement specifications. Material 13CrMo44, 90° R=2,400 mm

Additional projects

ImprintData ProtectionGeneral Terms and ConditionsDownloads for Business Partners