Decentralised power generation, hot water and steam supply

Beck & Co. steam generation plant, Bremen

The traditional Beck & Co. brewery secured its future with the investment in a new power generation system: To safeguard the generation of power, a state-of-the-art steam generator was added to the existing boiler plant. Three existing power plant boilers were upgraded to the state-of-the-art with the latest control technology. An optimised operating and visualisation system was installed in the power plant control centre.

With the complete engineering service, the procurement and erection of all plant components all the way to commissioning and documentation, Beck & Co received a new, efficient heat generation system from a single source.

Fact sheet

Customer:
Brauerei Beck GmbH & Co. KG

Period of execution:

  • Order placed: 04/2003
  • Commissioning: 11/2003
  • Handover to the customer: 01/2004

Plant parameters:

  • 1 steam generator 30 t/h, 12 barg, 240 oC
  • Fuel: Natural gas H