Industrial plants, new plant construction, conversions and modifications

Construction of an exhaust gas cooler in a silicon factory

Wacker Chemicals Norway is building a new smelting furnace for silicon metal at its site in Holla, Norway. The exhaust gases from the melting furnace are passed through a cooling system (trombone cooler) before they are treated with dust. 

For the realisation of this EPC project, the solution areas of Industrial Plants (project management, installation, system check out), Engineering (engineering) and Fabrication (400 t pipelines made from 1.4841 / DN900 and 10CrMo9-10 / DN800) of the Kraftanlagen Group have combined to offer Wacker Chemicals Norway an optimum package.

The range of services includes the complete engineering including calculation and preparation of production drawings, project management, fabrication including material purchasing, packaging, shipping and unloading of a total of 600 t of material as well as installation, scaffolding, crane services, corrosion protection and system check out.

Fact sheet

Fact sheet
Customer:
Wacker Chemicals Norway AS

Duration:
1 year

Scope of performance:
• Complete engineering, calculation and preparation of production drawings
• Project management
• Material purchasing, fabrication, packaging and shipping of a total of 600 t of material
• Installation, scaffolding, corrosion protection and system check out